Kolkata Metro Expansion Faces Major Delays Due to Land and Clearance Issues, Railways Minister Informs Parliament

Date:

The Ministry of Railways has revealed to Parliament that several key expansion corridors of the Kolkata Metro are significantly delayed. The primary reasons cited include land acquisition hurdles, removal of encroachments, and pending clearances from the West Bengal Government.

Currently, 52 kilometers of new metro lines are under construction in and around Kolkata. However, as Railways Minister Ashwini Vaishnaw stated in a written reply in the Lok Sabha, approximately 20 kilometers of these projects remain stalled.

The Joka–Esplanade corridor, one of the crucial expansion lines, exemplifies these challenges. While the 7.74-km Joka–Majerhat section is operational, construction beyond Majerhat up to Esplanade continues to face delays.

A notable bottleneck has been land acquisition issues at Khidderpur, where land owned by the Kolkata Armed Police was required for the project. Approval for this land was pending for nearly five years and was only granted in July 2025, further pushing back progress.

Minister Vaishnaw’s disclosure underscores the complex administrative and logistical challenges facing urban infrastructure projects in the region, with hopes pinned on timely government cooperation to accelerate completion.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Share post:

spot_img

Popular

More like this
Related

India Achieves Historic $10 Billion Smartphone Export Milestone in Q1

India has set a new record for smartphone exports...

India Opens New Rail Trade Corridor with First Direct Commercial Container Freight Train to Nepal

Giving a major boost to India-Nepal trade, Indian Railways...

Innovation to Drive the Next Phase of India’s Pharma Growth, Says Union Minister

Union Minister of Commerce and Industry Piyush Goyal stated...

Centre Eyes Bigger Global Toy Market Share with New Task Force

Union Minister of Commerce and Industry Piyush Goyal has...